Road Improvement Updates 2021

ROAD PAVING UPDATES: July 8, 2021

The Town's road resurfacing contractor has begun work on the following streets:

  • Manitou Circle
  • Marlin Court
  • Unami Terrace
  • Mohican Drive
  • Carol Drive
  • Davis Court
  • Wychview Drive
  • Hampton Court
  • Karen Terrace

Manhole casting replacements will be completed first on these roads, followed by milling and paving in the coming weeks.


----------------------------------------



ROAD PAVING UPDATES: June 3, 2021

 

▪ Elizabethtown Gas' paving contractor, Atlantic Infrastructure, expects to begin the road resurfacing process, including milling and paving, of Lawrence Avenue (from Roanoke Road to the Town line), as early as Friday, June 4. As a result, access to Route 22 off of Lawrence Avenue will be restricted at times; please plan accordingly.
 
▪ Additional roads where paving will follow are listed below. Notices will be distributed in these areas by Atlantic Infrastructure prior to the work commencing.
✅ Orenda Circle (entire length)
✅ Roanoke Road (entire length)
✅ Quantuck Lane (entire length with drainage)
✅ Hiawatha Drive (entire length with drainage)
✅ Woods End Road (entire length)
 

 

ROAD PAVING UPDATES: May 12, 2021

 
Utility Company Paving Work
▪ Elizabethtown Gas' paving contractor, Atlantic Infrastructure, expects to begin the road resurfacing process, including milling and paving, of Birch Avenue (entire length) and Highland Avenue (Hillside to Sinclair) as early as Thursday, May 13. Notices have been distributed to affected homes.
 
▪ Additional roads that will follow in the coming weeks are listed below. Notices will be distributed in these areas by Atlantic Infrastructure prior to the work commencing.
✅ Standish Avenue (Mountainview Terrace to Colonial)
✅ Cedar Terrace (entire length)
✅ Hillside Avenue (entire length)
✅ Mountainview Circle (entire length)
✅ Bradford Avenue (Cedar to Colonial)
✅ Colonial Avenue (entire length)
✅ Sinclair Place (Lawrence to Highland)
✅ Orenda Circle (entire length)
✅ Roanoke Road (entire length)
✅ Quantuck Lane (entire length with drainage)
✅ Hiawatha Drive (entire length with drainage)
✅ Lawrence Avenue (Roanoke to Town Line)
✅ Woods End Road (entire length)
 
 
Municipal Paving Work
▪ The Town will pave additional roads in this area through a separate contractor/public bidding process to complete the grid, with specific timing to follow:
✅ Standish Avenue (Colonial to Alden)
✅ Bradford Avenue (Colonial to Mountain)
✅ Alden Avenue (entire length)
✅ Highland Avenue (Sinclair to Dudley)
✅ Dudley Court (entire length)
 
As always, all work is weather permitting. For a full list of planned and completed paving work for 2021-2024, please visit the Road Improvements page.